Project Location
Ordu / Türkiye
Year of Construction
2012 - 2011
Project Category
Multi-Storey Carpark
Project Scope Of Bid
Turnkey Lumpsum

Work Title :

Yenimahalle Multi-Storey Parking And Social Facilities

Employer:

Ordu Municipality

Current Status :

Completed
Job identifier
Project Location Ordu / Türkiye
Project Work Group Superior Structure
Project Category Multi-Storey Carpark
Project Scope Of Bid Turnkey Lumpsum
The employer of the project, which was started on 28.01.2011 and completed on 01.08.2012, is Ordu Municipality. The project, which consists of a 4-storey Multiple Parking Lot, cafeteria, shop, landscaping, square and seating areas, includes concrete construction, architectural and finishing works, mechanical and electrical works.

Project information
Date Of Contract 28.01.2011
Date Of Completion 01.08.2012
Completion Time 551 Day
Construction Area 14.000 m2
Inside; The building, which includes a Hot Glass Workshop, Youth Center, Library, Course Centers and Marketplaces, also continues to serve as a Social Facility.