Project Location        
Afyon / Merkez
Year of Construction
2001- 1998
Project Work Group
Superior Structure
Project Category
Military Facilities

Work Title

500Th Fortification Main Depot Command Ammunition Storage Facility And iglos

Employer

Ministry Of National Defence

Actual Status

Completed
Job Identifler
Project Location        Afyon / Merkez
Project Work Group Superior Structure
Project Category Military Facilities
ProJect Scope Of Bid Turnkey Lumpsum

The employer of the project, the contract of which was signed on 15.08.1998, is the MINISTRY OF NATIONAL DEFENSE. The project, which consists of 42 igloos and 5 large ammunition depots, includes a Test Center and Vehicle and Weapon systems storage bunkers.

Project Information
Date Of Contract 15.08.1998
Date Of Completion 8.07.2001
Completion Time 1058 Day
Total Length Of Line 88.000 m2

Within the scope of the project, ammunition and weapons that are in the inventory of the Ministry of National Defense and the Turkish Armed Forces and that will be included in the inventory are preserved.