The employer of the project, which was started in 1991 and completed in 1994, is the General Directorate of Iller Bank. Infrastructure includes drinking water line and connections.

Project Information
Date Of Contract 13.06.1991
Date Of Completion 16.06.1995
Completion Time 1444 Day
Total Length Of Line 88 Km
POLYETHYLENE pipes, which are produced from HDPE plastic and whose pipe diameters vary between 300 and 2000 bars, were used in the project, which also has horizontal drilling transitions in city connections.