Loading...
Project Location        
Konya-Beysehir / Türkiye
Year of Construction
2020-2016
Project Work Group
Transportation
Project Category
Highways

Work Title

Konya Beyşehir State Road

Employer

Highways Konya 3 Rd Regional Directorate

Actual Status

Completed
Job Identifler
Project Location        Konya-Beysehir / Türkiye
Project Work Group Transportation
Project Category Highways
ProJect Scope Of Bid Offer Unit Price
Employer of the project whose contract was signed on 20.08.2016 is the 3rd Reigonal Directrote of Highways in Konya. The project consist of 3 stages between 18-23 km’s, 33-55 km’s and 65-93 km’s. It includes earthworks, art structures, superstructures and bituminous hot mix asphalt works.

Project Information
Date Of Contract 20.08.2016
Date Of Completion 10.12.2020
Completion Time 1573 Day
Total Length Of Road 93 Km

The double road, which connects Konya to Beyşehir and is 93 km long, has been put into service as a divided road with a bandwidth of 12 meters.